NORTH BARSTOW STREET
CONSTRUCTION INFORMATION

Cone.png

What's Happening?

Street Improvement Project –

Phase Two Begins May 28

Starting Tuesday, May 28, the City of Eau Claire will begin Phase Two of the street improvement project that started in the North Barstow business neighborhood on April 14. This phase will close North Barstow Street from Madison Street to the riverfront near the Andante Apartments. During construction the sidewalks will remain open to access businesses.

Timeline:
Construction is expected to be completed around June 20.

Access During Construction:
Galloway Street will remain open for crossing Barstow, allowing continued access to local businesses, Phoenix Park, and the North Barstow parking ramp -- which will be free to use during this period.

Project Work Includes:

  • Removing pavers from crosswalks and replacing them with stamped concrete

  • Replacing select sections of sidewalk and installing pavers in boulevard areas

  • Upgrading ADA ramps at corners

  • Repairing or replacing sections of curb and gutter

  • Adjusting manhole covers

  • Map with details can be viewed here.

PDF maps from the city, including estimated timelines and closure details, are available below.

May 16 - May 24

May 27 - June 20

June 9 - June 20

June 20 - June 30​

North Barstow Construction Map.png

Click Picture or Here to View Larger

Questions? Concerns?

If you have any questions, concerns or issues email

Al Rinka, Deputy City Engineer:

al.rinka@eauclairewi.gov