Go backPosted: June 12, 2013 Tentative South Barstow Street Construction Schedule
Remember this schedule is TENTATIVE and can change:
S. Barstow Street - Lake Street to Eau Claire Street
- Removal of street light poles has been completed.
- Concrete removal has been completed.
- Storm sewer was to be completed by Monday, June 10th.
- Grading and graveling from Lake Street to E. Grand Avenue was to be completed by Friday, June 7th.
- Electrical/sound/irrigation conduit began on Monday, June 1st.
- Curb and gutter from Lake Street to E. Grand Avenue is tentatively scheduled for Tuesday, June 11th.
- Light pole bases from Lake Street to E. Grand Avenue are tentatively scheduled for Thursday, June 13th.
- Sidewalk replacement from Lake Street to E. Grand Avenue is tentatively scheduled for Monday, June 17th.
- Concrete pavement is tentatively scheduled for Wednesday, June 26th.