Tentative Timeline for the Next Couple of Weeks-written May 31, 2013
 
Remember this schedule is TENTATIVE and can change:
 
S. Barstow Street - Lake Street to Eau Claire Street
  • Removal of street light poles has been completed
  • Concrete removal to be completed early next week
  • Sawing of the sidewalk to be completed by the end of next week
  • Storm sewer work began on Wednesday
  • Grading and graveling from Lake Street to E. Grand Avenue is tentatively scheduled for Monday, June 3rd
  • Electrical/sound/irrigation conduit is tentatively scheduled for Monday, June 1st
  • Curb and gutter from Lake Street to E. Grand Avenue is tentatively scheduled for Tuesday, June 11th

 