Work completed since last update:

 

  • Began removing existing steel girders
  • Began hauling out removal material (concrete, steel, etc.)
  • Placed safety fence and gates on the west end of the project
  • Continued bridge deck demolition

 

Anticipated work schedule for the week of September 28:

 

  • Remove existing west abutment and piers
  • Continue bridge deck demolition
  • Continue removing existing steel girders
  • Continue hauling out removal material (concrete, steel, etc.)