August 16, 2019

Changes/additions from last week in orange

Downtown Riverwalk Wall

Completed

Haymarket Plaza - Open to PUblic

Items yet to be completed:
Wiring for fire feature controls.
Controllers need to be installed prior to stepper light activation in lawn area.
Concrete bollards to be placed at the end of Gibson Street for the trail behind Pablo Center. 


Street Improvements

Lake Street (Farwell to Chippewa River Bridge)

Removals have been completed.
Storm sewer has been completed.
Grading and graveling
 has been completed.
Concrete signal
bases and light bases have been completed. 
Concrete curb and sidewalks
have been completed. 
Concrete pavement has been completed.
Brick paver boulevards to be completed by Friday, August 16th. 
Sealing concrete pavement joints has been completed. 
Pavement marking is scheduled to begin on Thursday, August 15th.
Signal and camera work to be done the week of August 19th. 
Street is scheduled to be open to traffic on Friday, August 23rd.  

LINK TO DETOUR MAP FOR LAKE STREET

Forest Street (Madison st. to Huyssen St.)

Tentativley scheduled to begin work on August 28th. 

State Street - South City Limits to Garfield Avenue

Fillmore Avenue to North side of Lexington Blvd.
Utility work has been completed.
Grading and graveling has been completed.
All concrete sidewalk, driveway approaches and curb to be completed by Friday, August 16th.
Grading to be completed by Wednesday, August 21st.
Paving of binder course at Lexington Blvd has been completed.
Paving of binder course is tentatively scheduled to begin on Wednesday, August 21st (2 days).
Adjusting manholes is scheduled for Friday, August 23rd (3 days).
Restoration of boulevards is scheduled for the week of August 26th.
Paving of surface is scheduled to begin on Thursday, August 29th (3 days).
Pavement marking is scheduled to begin on Wednesday, September 4th (2 days).
Roadway is tentatively scheduled to be open from Lexington Blvd to Fillmore Avenue by
September 10th.

Lexington Boulevard to Garfield Avenue
Retaining walls:
      East side retaining wall has been completed.
      West side retaining wall is scheduled to begin the week of August 12th.
54-Inch storm sewer has been completed.
Roadway is scheduled for closure from the s. side of Garfield Avenue to Bartlett Court
beginning on Thursday, July 25th. (Xcel Energy gas main work is scheduled for completion by
Tuesday, August 27th.)
Removal of pavement began the week of August 12th.
Water main is scheduled to begin on Wednesday, August 28th.
Sanitary sewer is scheduled to begin on Tuesday, September 3rd.
Services are scheduled for Friday, September 6th.
Storm sewer is scheduled for the week of September 9th.
Garfield Avenue to remain open until after Labor Day.

Hamilton Avenue Intersection

Tentatively scheduled to begin on Thursday, September 12th.

Milling and Asphalt Paving

Water Street – Sixth Avenue to Ninth Avenue:

Project complete with the exception of street light installation. 

FARWELL/GIBSON STREET PARKING RAMP

The City’s contractor, RAM Construction, continues repairs to the Farwell/Gibson Parking Ramp located adjacent to the Lismore Hotel. It is our intention to keep the ramp OPEN during construction, with partial level closures and single exit lane closures being possible throughout the summer months to complete the needed repairs. Please excuse our dust and be considerate of our workers, we will try to minimize the inconvenience.