Construction Updates

Construction Updates - November 16

Changes from the previous week are highlighted.

* There will be one last Construction Update for 2018 on November 30 before returning again for the 2019 season! *


Grand Ave Footbridge:

  • Bridge construction is complete with the exception of architectural lighting.
    • Architectural lighting is tentatively scheduled for installation in November.
  • The bridge is open on both sides and bicycle traffic is allowed.   

Graham Avenue:

  • Graham Avenue - Eau Claire Street to Lake Street - CONSTRUCTION SUBSTANTIALLY COMPLETE!
    • Street sign installation to be completed the week of November 19th.
    • Sealing of concrete joints to be completed as weather permits.
  • CONSTRUCTION ALSO COMPLETE:
    • E Grand Avenue - Graham Avenue to pedestrian bridge
    • Main Street - Barstow Street to Graham Avenue
    • Gray Street - Barstow Street to west end near River 

Downtown Riverwalk Wall

  • Bridge installation is complete and open to pedestrians! 
  • Bridge and wall/trail lighting will not be available until power is run from Xcel Energy, tentatively scheduled for the week of November 19th. 
  • Railing installation is scheduled for mid-December.  
  • Final staining of the retaining wall to be completed in 2019 due to cold temperatures.

Haymarket Plaza

  • Utilities - CONSTRUCTION COMPLETE! 
  • Seat Walls and Fire Feature Walls and Fountain:
    • Pouring of seat walls and fire features have been completed with the exception of the SW seat wall, to be completed in 2019.
    • Plumbing for fountain has been completed. 
    • Fire feature gas piping work has been completed.
      • Burner assemblies are in production, estimated for week of November 19th.
    • Seat wall cap installation along Haymarket Landing is scheduled for when weather permits.
    • Holiday Tree base has been completed. 
    • Placement of limestone blocks is scheduled to begin the week of November 12th.  
  • Concrete paving:
    • Concrete connecting Confluence Crossing Bridge to Pablo Center has been completed. 
    • Temporary pedestrian fencing has been installed.
    • Granite paver installation began on October 29th. 
      • Paver stone bands are complete. 
      • Fire feature patios to be completed in the spring.
    • Removable bollard installation at Plaza entrance has been completed.  
    • Bean paving to be completed in the spring.
  • Phoenix Park Landing - CONSTRUCTION COMPLETE!
    • Plantings to be done in the spring. 
  • Electrical cabinets:
    • Cabinets 1, 2, and 3 have been installed. 
    • Waiting for Xcel Energy to power up.

Harding Ave./Washington St.

  • Harding Ave. - Washington to Lee Street - CONSTRUCTION COMPLETE! 
    • Pedestrian signage to be installed in November.
  • Washington Street – Harding Avenue to Farwell Street - CONSTRUCTION COMPLETE!