July 19, 2019

Changes/additions from last week in orange

Downtown Riverwalk Wall

Completed

Haymarket Plaza - Open to PUblic

Pouring of seat walls has been completed.
Seat wall caps to be completed by the end of July.
Fire feature gas piping work has been completed, Xcel Energy needs to install new gas meter prior to startup. 
Paving of Fountain as been completed. 
Concrete Paving: Complete
Restoration/Plantings: Complete
Electical and lighting: Complete; contreollers need to be installed prior to startup.
Trail behind Pablo Center: Scheduled for pouring the week of July 22nd. 

Street Improvements

Lake Street (Farwell to Chippewa River Bridge)

Removals have been completed.
CINC conduit installation began on Wednesday, June 19th. 
Storm sewer
has been completed.
Grading and graveling
 has been completed.
Concrete signal
bases have been completed. 
Concrete sidewalk and gutter: 
     Curb and Gutter has been completed.
     North Side of Lake Street sidewalks have been completed.
     
South Side of Lake Street sidewalks scheduled for Monday, July 22nd. 
Concrete pavement is tentativley scheduled for the week of July 22nd.
Pavement marking is scheduled for August 14th. 

LINK TO DETOUR MAP FOR LAKE STREET


West Grand Avenue (First Ave. to Oxford Ave.)

Construction has been completed. 

State St (bartlett court to lexington blvd)

Retaining wall work began on June 26th. Pavement will remain during retaining wall work.
Storm sewer has been completed.
Roadway is scheduled for closure on th S. Side of Garfield Ave to Bartlett Court beginning on July 25th. 
Gas main work is scheduled to begin on July 25th. 

STATE ST (LEXINGTON BLVD to Fillmore ave)

Concrete sidewalk work will be taking place beginning the week of July 22nd.
Grading and graveling to be completed following utility work the week of July 22nd.

Tyler Avenue Intersection:
     Sanitary sewer has been completed.
     Water main has been completed.
     Services are scheduled for completion by Friday, July 19th.
     Storm sewer has been completed.

Grant Avenue Intersection:
     Sanitary sewer has been completed.
     Water main has been completed.
     Storm sewer has been completed.

MacArthur Avenue to Lexington Boulevard:
     Sanitary sewer has been completed.
     Water main has been completed.
     Storm sewer has been completed.
     Services are scheduled for completion by Friday, July 19th.
     Concrete curb and gutter is tentatively scheduled to begin on Thursday, July 25th.
     Concrete sidewalks and islands are tentatively scheduled for the week of July 29th.

Polk Avenue Intersection:
     Sanitary sewer has been completed.
     Water main has been completed.
     Services are scheduled for Monday, July 22nd (1 days).
     Storm sewer has been completed.

Lexington Boulevard Intersection:
     Grading and graveling has been completed.
     Concrete sidewalk construction has been completed.
     Concrete curb and gutter and islands are scheduled for completion by Monday, July 22nd.
     Xcel Energy and Charter Communications are scheduled for utility relocations by August
     9th (2 poles in intersection that need moving).
     Paving of binder course is scheduled to follow utility relocations.


Milling and Asphalt Paving

Water Street – Sixth Avenue to Ninth Avenue:
Xcel Energy scheduled to begin gas main work on June 17th. 
Concrete repairs have been completed. 
Light bases are scheduled for the week of July 22nd.
Milling is scheduled for July 24th.
Paving is scheduled for July 25th.
Pavement marking is scheduled for July 29th. 

FARWELL/GIBSON STREET PARKING RAMP

Beginning July 8th, 2019 the City’s contractor, RAM Construction, will be starting repairs to the Farwell/Gibson Parking Ramp located adjacent to the Lismore Hotel.
It is our intention to keep the ramp OPEN during construction, with partial level closures and single exit lane closures being possible throughout the summer months to complete the needed repairs.
Please excuse our dust and be considerate of our workers, we will try to minimize the inconvenience.