Tentative South Barstow Street Construction Schedule

Posted June 12th, 2013

Remember this schedule is TENTATIVE and can change:
S. Barstow Street - Lake Street to Eau Claire Street
  • Removal of street light poles has been completed.
  • Concrete removal has been completed.
  • Storm sewer was to be completed by Monday, June 10th.
  • Grading and graveling from Lake Street to E. Grand Avenue was to be completed by Friday, June 7th.
  • Electrical/sound/irrigation conduit began on Monday, June 1st.
  • Curb and gutter from Lake Street to E. Grand Avenue is tentatively scheduled for Tuesday, June 11th.
  • Light pole bases from Lake Street to E. Grand Avenue are tentatively scheduled for Thursday, June 13th.
  • Sidewalk replacement from Lake Street to E. Grand Avenue is tentatively scheduled for Monday, June 17th.
  • Concrete pavement is tentatively scheduled for Wednesday, June 26th.