This tentative schedule of the progress and expected week was updated on June 6th
  • Removal of street light poles has been completed.
  • Concrete removal has been completed.
  • Storm sewer to be completed by Monday, June 10th.
  • Grading and graveling from Lake Street to E. Grand Avenue to be completed by Friday, June 7th.
  • Electrical/sound/irrigation conduit began on Monday, June 1st.
  • Curb and gutter from Lake Street to E. Grand Avenue is tentatively scheduled for Tuesday, June 11th.
  • Light pole bases from Lake Street to E. Grand Avenue are tentatively scheduled for Thursday, June 13th.
  • Sidewalk replacement from Lake Street to E. Grand Avenue is tentatively scheduled for Monday, June 17th.
  • Concrete pavement is tentatively scheduled for Wednesday, June 26th.