Posted: September 11, 2015 Water Street bridge Construction Update

You can also find project information and photos (when we start adding them) by clicking HERE 


If the weather cooperates, we anticipate beginning bridge demolition next week.

Work this week:  

  • Traffic control installed
  • Erosion control placement
  • Mobilization to project
  • Began clearing trees

Anticipated work schedule for the week of Sept. 9-16, 2015:

  • Clearing and grubbing trees and brush
  • Continue to mobilize to site
  • Disconnect water main from existing bridge
  • Begin bridge deck demolition

Schedule:  Start Sept. 8, 2015- Sept. 1, 2016

Cost:  $7,086,957.60

Traffic impact:  Closed to traffic (Traffic detoured via Lake Street)