Go back

Posted: October 15, 2015 Water Street bridge Construction Update

The Department of Transportation has a page devoted to the Water Street bridge.  
Plus, you can sign up to receive weekly updates like this:    
Work completed since last update:

Cutting of existing steel girders for removal

Removed existing piers 1 & 2

Began excavating for west abutments and grading to footing elevation

Began sheeting for cofferdam at pier 2

Began setting temporary pedestal for Water Street/1st Avenue

Continued hauling out removal material (concrete, steel, etc.)

Continued mobilizing to the project

Anticipated work schedule through October 16:

Begin west abutment formwork, formliner, and reinforcing steel

Begin pier 2 footing pile driving

Begin west abutment form stripping

Begin sheeting for cofferdam at pier 1

Pour concrete for body of west abutment

Click HERE to Visit the DOT's project page and sign up for updates!

Send this blog post to someone: