Construction Updates

Construction Updates September 14-21


Grand Ave Footbridge:

  • Bridge construction is complete (!!!) with the exception of architectural lighting.
    • Architectural lighting is tentatively scheduled for installation the week of September 24th.
  • The bridge is open on both sides and bicycle traffic is allowed.   

Graham Ave./ Main St./ Gray St. 

  • Graham Avenue - Eau Claire Street and Lake Street. 
    • Utility work has been completed. 
    • Grading and graveling has been completed. 
    • Curb and gutter has been completed. 
    • Sidewalk installation has been completed. 
    • Concrete pavement:
      • From Gibson St. to Gray St.. has been completed.
      • From Gray St. to Lake St. paving will start the week of September 24th. 
    • Brick paver boulevards:
      • Completed from Eau Claire St. to Gibson St.
      • Completed from Gibson St. to E Grand Ave. 
      • E Grand Ave. to Main St. to be completed by September 15th. 
    • Brick paver crosswalks: 
      • Gibson St. intersection complete. 
      • E Grand Ave. intersection complete.
      • Main St. to be completed by Saturday, September 22nd. 
    • Concrete boulevard installation has been completed from Gibson St. to E Grand Ave., and from E Grand Ave. to Main St. 
  • E Grand Avenue - Graham Ave. to pedestrian bridge
    • Completed! 
  • Main Street - Barstow Street to Graham Avenue 
    • Concrete pavement has been completed. 
    • Brick paver boulevards to be completed the week of September 24th. 
  • Gray Street - Barstow Street to west end near River 
    • Sidewalks have been completed.
    • Concrete pavement is scheduled for the week of September 24th. 
    • Brick paver boulevards are scheduled for the week of September 24th. 
  • Lake Street intersection is re-opened!  

Downtown Riverwalk Wall

  • Confluence Crossing Bridge, Haymarket Plaza & Riverwalk construction work will be steady in and around the plaza and bridge area through November. 
  • Bridge installation is complete and scheduled to open to pedestrians! 
  • Bridge lighting will not be available until power is run from Xcel Energy.
  • Backfilling of Plaza has been completed.
  • Final pour of retaining walls has been completed. 
  • Staining of the retaining wall is scheduled to begin the week of September 4th. 
  • Crane has been removed from site 
  • Steps are scheduled for completion on Friday, September 21st. 
  • Railing installation is scheduled for the week of October 8th. 

Haymarket Plaza

  • Utilities:
    • Sanitary service for fountain has been installed. 
    • Water service for the fountain hook up is completed. 
    • Power and fiber conduits installation have been installed at all cabinet base locations.
    • Storm sewer work has been completed.
    • Installation of gas lines has been completed.
    • Irrigation system installation to continue with construction as needed. 
    • Temporary pedestrian fencing has been installed. 
  • Seat Walls and Fire Feature Walls:
    • Pouring of seat walls along Haymarket Landing has been completed. 
    • Pouring of fire walls near Pablo Center has been completed.
    • Pouring of footings for bean walls have been completed. 
    • Forming of bean walls has been completed. 
    • Pouring of final bean wall is scheduled for Friday, September 21st. 
    • Excavation of fountain area is scheduled for the week of September 24th. 
    • Excavation for final fire feature is scheduled for the week of September 24th. 
  • Concrete paving:
    • Pouring of concrete surface on the north side of the Pablo Center has been completed. 
      • Paving stone bands are scheduled for the week of October 1st.
      • Band areas to be filled in to grade for access. 
    • Grading and graveling from the pedestrian bridge south has been completed. 
    • Concrete connecting Confluence Crossing Bridge to Pablo Center has been completed. 
  • Phoenix Park Landing:
    • Grading and graveling has been completed.
    • Concrete borders have been completed. 
    • Installation of brick pavers has been completed. 
    • Restoration to be done the week of September 24th.  
  • Electrical cabinets:
    • Pouring of the base near pedestrian bridge (Cabinet 2) has been completed.  
    • Pouring of the base near Haymarket Landing (Cabinet 1) has been completed.
    • Cabinets to be installed beginning the week of September 24th. 
  • Graham Avenue & Eau Claire Street intersection 
    • Curb and gutter, sidewalk, and concrete paving have been completed. 
    • Installation of brick pavers in boulevard are scheduled for Friday, September 21st.
    • Intersection is scheduled to be open to traffic the afternoon of Friday, September 21st. 

Harding Ave./Washington St.

  • Harding Ave. - Washington to Lee Street - CONSTRUCTION COMPLETE! 
  • Washington Street – Harding Avenue to Farwell Street - CONSTRUCTION COMPLETE! 

Sign up for weekly construction updates here.